Design as of 8/16

As of 8/16 (also the start of school!! welcome back students of SCHS), the design for the expansion is in limbo. We are waiting to see what happens with the budget and what we will have to cut in the project. We will start the procurement of materials once the budget is confirmed. We can expect this all to happen in mid-September, followed by the permitting process in November. However, regardless of budgeting and design, we plan on starting construction of the expansion as soon as school lets out of the 17-18 year. 